Facts and Time Schedule

​General Hospital (Akuthus):

  • DKK 3.35bn. ~ € 450m
  • Construction: 75,500 m2
  • Refurbishments: 12.000 m2

Time Schedule

The hospital must operate at full capacity during the whole construction period. Therefore, the construction process has been planned thoroughly and will be executed over a period of ten years.The hospital will be constructed in stages and is scheduled to be finished in 2026.